>> 自然科学版期刊 >> 2023 >> 2023年01期 >> 正文
立井冻结黏土爆破对井壁的振动影响研究
时间: 2023-01-10 次数:

于建新, 李真珍, 郭敏, .立井冻结黏土爆破对井壁的振动影响研究[J].河南理工大学学报(自然科学版),2023,42(1):26-34.

YU J X, LI Z Z, GUO M,et al.Study on the influence of vertical shaft blasting with frozen clay on the vibration of shaft wall[J].Journal of Henan Polytechnic University(Natural Science) ,2023,42(1):26-34.

立井冻结黏土爆破对井壁的振动影响研究

于建新1, 李真珍1, 郭敏2, 张英才1

1.河南理工大学 土木工程学院,河南 焦作  4540002;中国建筑第二工程局有限公司 第二建筑工程有限公司,河南 郑州  450000

摘要:立井采用冻结法施工时,冻结黏土爆破产生的振动易引起井壁破裂,从而造成安全事故。以赵固二矿立井冻结黏土爆破掘进工程为背景,运用ANSYS/LS-DYNA数值模拟软件建立模型,研究不同掏槽药量、地应力条件、中空孔数量工况下爆破振动对井壁产生的影响。结果表明:井壁测点振速与掏槽药量成正比,掏槽药量从16 kg增加至64k g,振速从9.53 cm/s增加至35 cm/s,增大了3.67倍;中空孔可减弱爆破冲击荷载对井壁的振动影响,且井壁振动速度与中空孔半径成反比;地应力在13 MPa变化时,井壁振动速度与地应力成正比。现场爆破方案数值模拟得出:采用1345段电雷管毫秒延时爆破时,冻结黏土爆破产生的应力波主要沿井壁竖向传递;4段辅助孔爆破对井壁的振动影响最大,约为5段周边孔爆破的3.5倍,在距离掘进面13.3 m处,4段辅助孔产生的拉应力最大为0.425 MPa,不会对井壁混凝土结构产生破坏。分析方法和研究结果可为同类型条件深大立井冻结黏土爆破施工提供参考。

关键词:冻结黏土爆破;赵固二矿;立井井壁;爆破振动;数值模拟

doi:10.16186/j.cnki.1673-9787.2021070022

基金项目:国家自然科学基金资助项目(42107200);河南省科技攻关计划项目(212102310598);中国职业安全健康协会创新创业项目(CXCY-2021-23

收稿日期:2021/07/05

修回日期:2022/01/20

出版日期:2023/01/25

Study on the influence of vertical shaft blasting with frozen clay on the vibration of shaft wall

YU Jianxin1, LI Zhenzhen1, GUO Min2, ZHANG Yingcai1

1.School of Civil EngineeringHenan Polytechnic UniversityJiaozuo  454000HenanChina;2.Second Bureau the Second Construction Company Ltd. of China ConstructionZhengzhou  450000HenanChina

Abstract:When the vertical shaft excavation is constructed by freezing technologythe frozen clay blasting will have a vibration effect on the shaft walland it is easy to cause rupture of shaft wallresulting in safety accidents.Taking the frozen clay blasting excavation project of Zhaogu No.2 Mine as the research backgroundthe ANSYS/LS-DYNA numerical simulation software was used to establish the modelthe influence of blasting vibration on shaft wall under different cutting dosageground stress conditions and the number of hollow holes was studied.The results showed that the vibration velocity of shaft wall measuring points was proportional to the cutting dosage.The cutting dosage increased by 4 times from 16 kg to 64 kgand the vibration velocity of the shaft wall measuring points increase by 3.67 times from 9.53 cm/s to 35 cm/s.Hollow hole could weaken the influence of blasting impact load on the vibration of the shaft walland the vibration velocity of the shaft wall was inversely proportional to the radius of the hollow hole.When the ground stress varies from 1 MPa to 3 MPathe vibration velocity of shaft wall was proportional to the ground stress.Numerical simulation analysis under field blasting scheme showed that the stress wave produced by frozen clay blasting was mainly transmitted along the vertical shaft wall when millisecond delay blasting of 134 and 5 segments of electric detonator was adopted.The blasting of four auxiliary holes had the most significant effect on the vibration of the shaft wallwhich was about 3.5 times of that of the five surrounding holes.At 13.3 m away from the working facethe maximum tensile stress produced by the four auxiliary holes was 0.425 MPawhich had no destructive effect on the concrete structure of the shaft wall.The analysis methods and research results could provide reference for frozen clay blasting construction of deep shaft under the same type of conditions.

Key words:frozen clay blasting;Zhaogu No.2 Mine;shaft wall;blasting vibration;numerical simulation

 004_2021070022_于建新_H.pdf

最近更新